Sec. 9. A creditor may not pay a contractor under a home improvement contract from the proceeds of a high cost home loan unless:

(1) the creditor is presented with a signed and dated completion certificate showing that the home improvements have been completed; and

(2) the instrument is payable to the borrower or jointly to the borrower and the contractor or, at the election of the borrower, through a third party escrow agent under a written agreement signed by the borrower, the creditor, and the contractor before the disbursement.

As added by P.L.73-2004, SEC.33.