Prohibited acts.

Checkout our iOS App for a better way to browser and research.

(1) Failure by a supplier of water to comply with the requirements of s. 403.857 or dissemination by such supplier of any false or misleading information with respect to notices required pursuant to s. 403.857 or with respect to remedial actions being undertaken to achieve compliance with state primary and secondary drinking water regulations.

(2) Failure by a supplier of water to comply with regulations adopted pursuant to s. 403.853, with any rule adopted by the department pursuant to this act, or with conditions for variances or exemptions authorized under s. 403.854.

(3) Failure by any person to comply with any order issued by the department pursuant to this act.

(4) Failure by a supplier of water to allow any duly authorized representative of the department or of the Department of Health to conduct inspections pursuant to s. 403.858.

(5) Submission by any person of any false statement or representation in any application, record, report, plan, or other document filed, or required to be filed by this act or rules adopted by the department pursuant to its lawful authority.

(6) Failure by a supplier of water to comply with the requirements of a permit issued under s. 403.861(7).

(7) The artificial recharge by the direct pumping of treated or untreated waste into any geologic formation of the Floridan Aquifer or the Biscayne Aquifer containing total dissolved solids of 500 milligrams per liter or less, except such injection of reclaimed water from domestic wastewater treatment reuse facilities if the effluent quality meets the water quality standards established by the Department of Environmental Protection as part of the operation permit to construct the treatment facility.

(a) By January 1, 1995, the Department of Environmental Protection shall promulgate by rule effluent standards and conditions for any project proposing wastewater reuse of reclaimed water, for injection of the reclaimed water into the Floridan Aquifer or Biscayne Aquifer. Any injection into a geologic formation of the Floridan Aquifer or Biscayne Aquifer containing total dissolved solids of 500 milligrams per liter or less must meet the requirements of these rules.

(b) In the event a facility does not receive, as a part of its operation permit, permission for injection which assures compliance with department rules promulgated pursuant to this subsection, the treated or untreated effluent shall be returned to the wastewater treatment plant from which the effluent was diverted during any testing period required by department rules or to another legally acceptable reuse or disposal alternative.

The provisions of this subsection do not apply to treated or untreated effluent currently discharging into the Floridan Aquifer or Biscayne Aquifer on June 22, 1983. However, any expansion of existing facilities on or after the effective date of this act are subject to the requirements of this subsection.

History.—s. 10, ch. 77-337; s. 164, ch. 79-400; s. 1, ch. 83-161; s. 3, ch. 94-153; s. 169, ch. 99-8; s. 5, ch. 2001-270.


Download our app to see the most-to-date content.