South Santa Clara County recycled water project

Checkout our iOS App for a better way to browser and research.

§390h–30. South Santa Clara County recycled water project

(a) Authorization

The Secretary, in cooperation with the South County Regional Wastewater Authority and the Santa Clara Valley Water District, is authorized to participate in the design, planning, and construction of recycled water system distribution facilities.

(b) Cost share

The Federal share of the cost of the project authorized by this section shall not exceed 25 percent of the total cost of the project.

(c) Limitation

The Secretary shall not provide funds for the operation and maintenance of the project authorized by this section.

(d) Authorization of appropriations

There is authorized to be appropriated to carry out this section $7,000,000.

(Pub. L. 102–575, title XVI, §1647, as added Pub. L. 110–229, title V, §512(a)(1), May 8, 2008, 122 Stat. 842 .)


Download our app to see the most-to-date content.