In a proceeding before a board of contract appeals, the United States Court of Federal Claims, or any other Federal court in which the reasonableness of indirect costs for which a contractor seeks reimbursement from the Federal Government is in issue, the burden of proof is on the contractor to establish that those costs are reasonable.
(
Revised Section | Source (U.S. Code) | Source (Statutes at Large) |
---|---|---|
4309 | 41:256(j). | June 30, 1949, ch. 288, title III, §306(j), as added
|