The Secretary shall, as soon as practicable after January 3, 1975, and after consultation with other Federal agencies, issue regulations to carry out the purposes and provisions of this chapter in accordance with the provisions of section 553 of title 5, without regard to subsection (a) thereof. Such regulations shall pertain to, but need not be limited to, application, issuance, transfer, renewal, suspension, and termination of licenses. Such regulations shall provide for full consultation and cooperation with all other interested Federal agencies and departments and with any potentially affected coastal State, and for consideration of the views of any interested members of the general public. The Secretary is further authorized, consistent with the purposes and provisions of this chapter, to amend or rescind any such regulation.
The Secretary, in consultation with the Secretary of the Interior and the Administrator of the National Oceanic and Atmospheric Administration, shall, as soon as practicable after January 3, 1975, prescribe regulations relating to those activities involved in site evaluation and preconstruction testing at potential deepwater port locations that may (1) adversely affect the environment; (2) interfere with authorized uses of the Outer Continental Shelf; or (3) pose a threat to human health and welfare. Such activity may thenceforth not be undertaken except in accordance with regulations prescribed pursuant to this subsection. Such regulations shall be consistent with the purposes of this chapter.
(1) Any person making an application under this chapter shall submit detailed plans to the Secretary. Within 21 days after the receipt of an application, the Secretary shall determine whether the application appears to contain all of the information required by paragraph (2) hereof. If the Secretary determines that such information appears to be contained in the application, the Secretary shall, no later than 5 days after making such a determination, publish notice of the application and a summary of the plans in the Federal Register. If the Secretary determines that all of the required information does not appear to be contained in the application, the Secretary shall notify the applicant and take no further action with respect to the application until such deficiencies have been remedied.
(2) Each application shall include such financial, technical, and other information as the Secretary deems necessary or appropriate. Such information shall include, but need not be limited to-
(A) the name, address, citizenship, telephone number, and the ownership interest in the applicant, of each person having any ownership interest in the applicant of greater than 3 per centum;
(B) to the extent feasible, the name, address, citizenship, and telephone number of any person with whom the applicant has made, or proposes to make, a significant contract for the construction or operation of the deepwater port and a copy of any such contract;
(C) the name, address, citizenship, and telephone number of each affiliate of the applicant and of any person required to be disclosed pursuant to subparagraphs (A) or (B) of this paragraph, together with a description of the manner in which such affiliate is associated with the applicant or any person required to be disclosed under subparagraph (A) or (B) of this paragraph;
(D) the proposed location and capacity of the deepwater port, including all components thereof;
(E) the type and design of all components of the deepwater port and any storage facilities associated with the deepwater port;
(F) with respect to construction in phases, a detailed description of each phase, including anticipated dates of completion for each of the specific components thereof;
(G) the location and capacity of existing and proposed storage facilities and pipelines which will store or transport oil transported through the deepwater port, to the extent known by the applicant or any person required to be disclosed pursuant to subparagraphs (A), (B), or (C) of this paragraph;
(H) with respect to any existing and proposed refineries which will receive oil transported through the deepwater port, the location and capacity of each such refinery and the anticipated volume of such oil to be refined by each such refinery, to the extent known by the applicant or any person required to be disclosed pursuant to subparagraphs (A), (B), or (C) of this paragraph;
(I) the financial and technical capabilities of the applicant to construct or operate the deepwater port;
(J) other qualifications of the applicant to hold a license under this chapter;
(K) the nation of registry for, and the nationality or citizenship of officers and crew serving on board, vessels transporting natural gas that are reasonably anticipated to be servicing the deepwater port;
(L) a description of procedures to be used in constructing, operating, and maintaining the deepwater port, including systems of oil spill prevention, containment, and cleanup; and
(M) such other information as may be required by the Secretary to determine the environmental impact of the proposed deepwater port.
(3) Upon written request of any person subject to this subsection, the Secretary may make a determination in writing to exempt such person from any of the informational filing provisions enumerated in this subsection or the regulations implementing this section if the Secretary determines that such information is not necessary to facilitate the Secretary's determinations under section 1503 of this title and that such exemption will not limit public review and evaluation of the deepwater port project.
(1) At the time notice of an application is published pursuant to subsection (c) of this section, the Secretary shall publish a description in the Federal Register of an application area encompassing the deepwater port site proposed by such application and within which construction of the proposed deepwater port would eliminate, at the time such application was submitted, the need for any other deepwater port within that application area.
(2) As used in this section, "application area" means any reasonable geographical area within which a deepwater port may be constructed and operated. Such application area shall not exceed a circular zone, the center of which is the principal point of loading and unloading at the port, and the radius of which is the distance from such point to the high water mark of the nearest adjacent coastal State.
(3) The Secretary shall accompany such publication with a call for submission of any other applications for licenses for the ownership, construction, and operation of a deepwater port within the designated application area. Persons intending to file applications for such license shall submit a notice of intent to file an application with the Secretary not later than 60 days after the publication of notice pursuant to subsection (c) of this section and shall submit the completed application no later than 90 days after publication of such notice. The Secretary shall publish notice of any such application received in accordance with subsection (c) of this section. No application for a license for the ownership, construction, and operation of a deepwater port within the designated application area for which a notice of intent to file was received after such 60-day period, or which is received after such 90-day period has elapsed, shall be considered until the application pending with respect to such application area have been denied pursuant to this chapter.
(4) This subsection shall not apply to deepwater ports for natural gas.
(1) Not later than 30 days after January 3, 1975, the Secretary of the Interior, the Administrator of the Environmental Protection Agency, the Chief of Engineers of the United States Army Corps of Engineers, the Administrator of the National Oceanic and Atmospheric Administration, and the heads of any other Federal department or agencies having expertise concerning, or jurisdiction over, any aspect of the construction or operation of deepwater ports shall transmit to the Secretary written comments as to their expertise or statutory responsibilities pursuant to this chapter or any other Federal law.
(2) An application filed with the Secretary shall constitute an application for all Federal authorizations required for ownership, construction, and operation of a deepwater port. At the time notice of any application is published pursuant to subsection (c) of this section, the Secretary shall forward a copy of such application to those Federal agencies and departments with jurisdiction over any aspect of such ownership, construction, or operation for comment, review, or recommendation as to conditions and for such other action as may be required by law. Each agency or department involved shall review the application and, based upon legal considerations within its area of responsibility, recommend to the Secretary, the approval or disapproval of the application not later than 45 days after the last public hearing on a proposed license for a designated application area. In any case in which the agency or department recommends disapproval, it shall set forth in detail the manner in which the application does not comply with any law or regulation within its area of responsibility and shall notify the Secretary how the application may be amended so as to bring it into compliance with the law or regulation involved.
For all applications, the Secretary, in cooperation with other involved Federal agencies and departments, shall comply with the National Environmental Policy Act of 1969 (42 U.S.C. 4332) [42 U.S.C. 4321 et seq.]. Such compliance shall fulfill the requirement of all Federal agencies in carrying out their responsibilities under the National Environmental Policy Act of 1969 pursuant to this chapter.
A license may be issued only after public notice and public hearings in accordance with this subsection. At least one such public hearing shall be held in each adjacent coastal State. Any interested person may present relevant material at any hearing. After hearings in each adjacent coastal State are concluded if the Secretary determines that there exists one or more specific and material factual issues which may be resolved by a formal evidentiary hearing, at least one adjudicatory hearing shall be held in accordance with the provisions of section 554 of title 5 in the District of Columbia. The record developed in any such adjudicatory hearing shall be basis for the Secretary's decision to approve or deny a license. Hearings held pursuant to this subsection shall be consolidated insofar as practicable with hearings held by other agencies. All public hearings on all applications for any designated application area shall be consolidated and shall be concluded not later than 240 days after notice of the initial application has been published pursuant to subsection (c) of this section.
(1) Each person applying for a license pursuant to this chapter shall remit to the Secretary at the time the application is filed a nonrefundable application fee established by regulation by the Secretary. In addition, an applicant shall also reimburse the United States and the appropriate adjacent coastal State for any additional costs incurred in processing an application.
(2) Notwithstanding any other provision of this chapter, and unless prohibited by law, an adjacent coastal State may fix reasonable fees for the use of a deepwater port facility, and such State and any other State in which land-based facilities directly related to a deepwater port facility are located may set reasonable fees for the use of such land-based facilities. Fees may be fixed under authority of this paragraph as compensation for any economic cost attributable to the construction and operation of such deepwater port and such land-based facilities, which cannot be recovered under other authority of such State or political subdivision thereof, including, but not limited to, ad valorem taxes, and for environmental and administrative costs attributable to the construction and operation of such deepwater port and such land-based facilities. Fees under this paragraph shall not exceed such economic, environmental, and administrative costs of such State. Such fees shall be subject to the approval of the Secretary. As used in this paragraph, the term "land-based facilities directly related to a deepwater port facility" means the onshore tank farm and pipelines connecting such tank farm to the deepwater port facility.
(3) A licensee shall pay annually in advance the fair market rental value (as determined by the Secretary of the Interior) of the subsoil and seabed of the Outer Continental Shelf of the United States to be utilized by the deepwater port, including the fair market rental value of the right-of-way necessary for the pipeline segment of the port located on such subsoil and seabed.
(1) The Secretary shall approve or deny any application for a designated application area submitted pursuant to this chapter not later than 90 days after the last public hearing on a proposed license for that area.
(2) In the event more than one application is submitted for an application area, the Secretary, unless one of the proposed deepwater ports clearly best serves the national interest, shall issue a license according to the following order of priorities:
(A) to an adjacent coastal State (or combination of States), any political subdivision thereof, or agency or instrumentality, including a wholly owned corporation of any such government;
(B) to a person who is neither (i) engaged in producing, refining, or marketing oil, nor (ii) an affiliate of any person who is engaged in producing, refining, or marketing oil or an affiliate of any such affiliate;
(C) to any other person.
(3) In determining whether any one proposed deepwater port clearly best serves the national interest, the Secretary shall consider the following factors:
(A) the degree to which the proposed deepwater ports affect the environment, as determined under criteria established pursuant to section 1505 of this title;
(B) any significant differences between anticipated completion dates for the proposed deepwater ports; and
(C) any differences in costs of construction and operation of the proposed deepwater ports, to the extent that such differential may significantly affect the ultimate cost of oil to the consumer.
(4) The Secretary shall approve or deny any application for a deepwater port for natural gas submitted pursuant to this chapter not later than 90 days after the last public hearing on a proposed license. Paragraphs (1), (2), and (3) of this subsection shall not apply to an application for a deepwater port for natural gas.
(
The National Environmental Policy Act of 1969, referred to in subsec. (f), is
2010-Subsec. (c)(2)(K).
2006-Subsec. (c)(2)(K) to (M).
2002-Subsec. (d)(4).
Subsec. (f).
Subsec. (h)(2).
Subsec. (i)(4).
1996-Subsec. (c)(3).
1984-Subsec. (g).
"(1)
"(2)
"(3)