Notwithstanding any other provision of law, the actions of Federal officers or agencies taken pursuant to section 719g of this title, shall not be subject to judicial review except as provided in this section.
(1) Claims alleging the invalidity of this chapter may be brought not later than the 60th day following the date a decision takes effect pursuant to section 719f of this title.
(2) Claims alleging that an action will deny rights under the Constitution of the United States, or that an action is in excess of statutory jurisdiction, authority, or limitations, or short of statutory right may be brought not later than the 60th day following the date of such action, except that if a party shows that he did not know of the action complained of, and a reasonable person acting in the circumstances would not have known, he may bring a claim alleging the invalidity of such action on the grounds stated above not later than the 60th day following the date of his acquiring actual or constructive knowledge of such action.
A claim under subsection (b) shall be barred unless a complaint is filed prior to the expiration of such time limits in the United States Court of Appeals for the District of Columbia acting as a Special Court.
The Special Court shall have exclusive jurisdiction to determine such proceeding in accordance with the procedures hereinafter provided, and no other court of the United States, or any State, territory, or possession of the United States, or of the District of Columbia, shall have jurisdiction of any such claim in any proceeding instituted prior to or on or after October 22, 1976.
The Special Court shall set any action brought under this section for expedited consideration, taking into account the national interest described in section 719 of this title.
The enactment of a joint resolution under section 719f of this title approving the decision of the President shall be conclusive as to the legal and factual sufficiency of the environmental impact statements submitted by the President relative to the approved transportation system and no court shall have jurisdiction to consider questions respecting the sufficiency of such statements under the National Environmental Policy Act of 1969 [42 U.S.C. 4321 et seq.].
(
The National Environmental Policy Act of 1969, referred to in subsec. (c)(3), is
2004-Subsec. (c).
Subsec. (c)(1).
Subsec. (c)(2).
Subsec. (c)(3).
1984-Subsec. (c)(2).
Amendment by
Enforcement functions authorized by, and supplemental enforcement authority created by this chapter with respect to pre-construction, construction, and initial operation of transportation system for Canadian and Alaskan natural gas transferred to Federal Inspector, Office of Federal Inspector for Alaska Natural Gas Transportation System, until first anniversary of date of initial operation of Alaska Natural Gas Transportation System, see Reorg. Plan No. 1 of 1979, §§102(h)(1), 203(a), 44 F.R. 33663, 33666,