Original estimates shall show in detail the estimated cost of the work; the estimated quantities of each class of work; the estimated unit cost for each class; the estimated total cost for each class; the time limit, allowed for the completion of the work and the estimated dates of commencement and completion.
[ 1986 c 282 § 3; 1923 c 183 § 4; RRS § 10322-4.]