Baseload renewable power portfolio requirement

Checkout our iOS App for a better way to browser and research.

§ 8009. Baseload renewable power portfolio requirement

(a) In this section:

(1) "Baseload renewable power" means a plant that generates electricity from renewable energy; that, during normal operation, is capable of taking all or part of the minimum load on an electric transmission or distribution system; and that produces electricity essentially continuously at a constant rate.

(2) "Baseload renewable power portfolio requirement" means an annual average of 175,000 MWh of baseload renewable power from an in-state woody biomass plant that was commissioned prior to September 30, 2009, has a nominal capacity of 20.5 MW, and was in service as of January 1, 2011.

(3) "Biomass" means organic nonfossil material of biological origin constituting a source of renewable energy within the meaning of subdivision 8002(17) of this title.

(4) [Repealed.]

(b) Notwithstanding subsection 8004(a) and subdivision 8005(d)(1) of this title, commencing November 1, 2012, the electricity supplied by each Vermont retail electricity provider to its customers shall include the provider's pro rata share of the baseload renewable power portfolio requirement, which shall be based on the total Vermont retail kWh sales of all such providers for the previous calendar year. The obligation created by this subsection shall cease on November 1, 2022.

(c) A plant used to satisfy the baseload renewable power portfolio requirement shall be a qualifying small power production facility under 16 U.S.C. § 796(17)(C) and 18 C.F.R. part 292.

(d) The Commission shall determine the price to be paid to a plant used to satisfy the baseload renewable power portfolio requirement. The Commission shall not be required to make this determination as a contested case under 3 V.S.A. chapter 25. The price shall be the avoided cost of the Vermont composite electric utility system. In this subsection, the term "avoided cost" means the incremental cost to retail electricity providers of electric energy or capacity, or both, which, but for the purchase from the plant proposed to satisfy the baseload renewable power portfolio requirement, such providers would obtain from a source using the same generation technology as the proposed plant. In this subsection, the term "avoided cost" also includes the Commission's consideration of each of the following:

(1) The relevant cost data of the Vermont composite electric utility system.

(2) The terms of the potential contract, including the duration of the obligation.

(3) The availability, during the system's daily and seasonal peak periods, of capacity or energy from a proposed plant.

(4) The relationship of the availability of energy or capacity from the proposed plant to the ability of the Vermont composite electric utility system or a portion thereof to avoid costs.

(5) The costs or savings resulting from variations in line losses from those that would have existed in the absence of purchases from the proposed plant.

(6) The supply and cost characteristics of the proposed plant, including the costs of operation and maintenance of an existing plant during the term of a proposed contract.

(e) In determining the price under subsection (d) of this section, the Commission may require a plant proposed to be used to satisfy the baseload renewable power portfolio requirement to produce such information as the Commission reasonably deems necessary.

(f) With respect to a plant used to satisfy the baseload renewable power portfolio requirement:

(1) The Standard Offer Facilitator shall purchase the baseload renewable power, and shall allocate the electricity purchased and any associated costs to the Vermont retail electricity providers based on their pro rata share of total Vermont retail kWh sales for the previous calendar year, and the Vermont retail electricity providers shall accept and pay those costs.

(2) Any tradeable renewable energy credits attributable to the electricity purchased shall be transferred to the Vermont retail electricity providers in accordance with their pro rata share of the costs for such electricity as determined under subdivision (1) of this subsection.

(3) All capacity rights attributable to the plant capacity associated with the electricity purchased shall be transferred to the Vermont retail electricity providers in accordance with their pro rata share of the costs for such electricity as determined under subdivision (1) of this subsection.

(4) All reasonable costs of a Vermont retail electricity provider incurred under this section shall be included in the provider's revenue requirement for purposes of ratemaking under sections 218, 218d, 225, and 227 of this title. In including such costs, the Commission shall appropriately account for any credits received under subdivision (2) of this subsection. Costs included in a retail electricity provider's revenue requirement under this subdivision shall be allocated to the provider's ratepayers as directed by the Commission.

(g) A retail electricity provider shall be exempt from the requirements of this section if, and for so long as, one-third of the electricity supplied by the provider to its customers is from a plant that produces electricity from woody biomass.

(h) The Commission may issue rules or orders to carry out this section.

(i) The State and its instrumentalities shall not be liable to a plant owner or retail electricity provider with respect to any matter related to the baseload renewable power portfolio requirement or a plant used to satisfy such requirement, including costs associated with a contract related to such a plant or any damages arising from the breach of such a contract, the flow of power between a plant and the electric grid, or the interconnection of a plant to that grid. For the purpose of this section, the Commission and the Standard Offer Facilitator constitute instrumentalities of the State. (Added 2011, No. 47, § 11; amended 2011, No. 170 (Adj. Sess.), § 9; 2015, No. 56, § 26.)


Download our app to see the most-to-date content.