73-31-203. Action by board on statutory water bank applications.
  • (1) Upon receipt of an application under Section 73-31-202, the board shall record the date the board receives the application.
  • (2) The board shall:
    • (a) examine an application for completeness to determine whether the application satisfies this part;
    • (b) review an application to determine whether it meets the objectives of a water bank described in Section 73-31-103;
    • (c) consider an application complete if the application satisfies the requirements of this part; and
    • (d) notify the applicant of any additional information or changes needed to process the application.
  • (3) Within 30 days of the date the board determines that an application is complete, the board shall post notice of the application pursuant to Section 73-31-103.
  • (4) The notice required by Subsection (3) shall state:
    • (a) that an application to create a statutory water bank has been filed with the board;
    • (b) where an interested party may obtain a copy of the application and any additional information related to the application; and
    • (c) the date, time, and place of the public meeting required by Section 73-31-204.