Interest rates.

Checkout our iOS App for a better way to browser and research.



  • (1) In controversies between a procurement unit and a contractor under this chapter, interest on amounts ultimately determined to be due to a contractor or the procurement unit are payable at the rate applicable to judgments from the date the claim arose through the date of decision or judgment, whichever is later.
  • (2) Unless otherwise specified in a lawful contract between a procurement unit and the person making a bond claim against the procurement unit, the interest rate applicable to the bond claim is the rate described in Subsection 15-1-1(2).
  • (3) This section does not apply to public assistance benefits programs.