Correcting an immaterial error in a solicitation response.

Checkout our iOS App for a better way to browser and research.



  • (1) A procurement unit may allow a vendor to correct an immaterial error in a responsive solicitation response as provided in this section.
  • (2)
    • (a) A procurement unit that allows a vendor to correct an immaterial error in a responsive solicitation response shall:
      • (i) require the vendor to submit the correction in writing; and
      • (ii) establish a deadline by which the vendor is required to correct the immaterial error.
    • (b) A procurement unit may not allow a vendor to correct an immaterial error in a responsive solicitation response after the deadline established under Subsection (2)(a).




Download our app to see the most-to-date content.