No limitation on other local entity powers -- Conflict with other statutory provisions.

Checkout our iOS App for a better way to browser and research.



  • (1) This chapter does not limit a power that a local entity has under other applicable law to:
    • (a) make an improvement or provide a service;
    • (b) create a district;
    • (c) levy an assessment or tax; or
    • (d) issue a bond or a refunding bond.
  • (2) If there is a conflict between a provision of this chapter and any other statutory provision, the provision of this chapter governs.
  • (3) After January 1, 2017, a local entity or the C-PACE district may create an energy assessment area within the certificated service territory of a public electrical utility for the installation of a renewable energy system with a nameplate rating of:
    • (a) no more than 2.0 megawatts; or
    • (b) more than 2.0 megawatts to serve load that the public electrical utility does not already serve.