Cross Connections, Auxiliary Intakes, By-Pass or Interconnections to Be Approved — Drain Lines or Conduits Carrying Wastes Not to Enter Water Supply
Checkout our iOS App for a better way to browser and research.
No person shall install, permit to be installed, or maintain any cross connection, auxiliary intake, by-pass, or interconnection, unless the source and quality of water from the auxiliary supply, the method of connection, and the use and operation of such cross connection, auxiliary intake, by-pass or interconnection has been approved by the department.
The arrangement of sewer, soil or other drain lines or conduits carrying sewage or other wastes in such manner that the sewage or waste may find its way into any part of the public water supply system is prohibited.