Duration of Lien

Checkout our iOS App for a better way to browser and research.

A prime contractor's lien shall continue for one (1) year after the date the improvement is complete or is abandoned, and until the final decision of any suit properly brought within that time for its enforcement.

Code 1858, § 1985 (deriv. Acts 1845-1846, ch. 118, § 1); Shan., § 3539; mod. Code 1932, § 7917; T.C.A. (orig. ed.), § 64-1106; Acts 2007, ch. 189, § 6.

Textbooks. Tennessee Jurisprudence, 18 Tenn. Juris., Mechanics' Liens, §§ 5, 14, 18, 23.

Law Reviews.

Mechanics' and Materialmen's Liens in Tennessee (Charles H. Barnett), 5 Mem. St. U.L. Rev. 359 (1975).


Download our app to see the most-to-date content.