49-41B-5. Notification of intent to apply for permit required before filing application--Time--Prefiling conference if applicant requests.

A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in §49-41B-11. A prefiling conference may be requested by the applicant and such request shall be granted by the commission.

Source: SL 1977, ch 390, §5; SL 2006, ch 242, §2.