49-41B-15. Commission procedure following receipt of application for permit.

Within thirty days following receipt of an application for a permit, the commission shall:

(1)Schedule a public input meeting;

(2)Notify the applicant of the public input meeting; and

(3)Serve notice of the application and public input meeting upon the governing bodies of the counties and municipalities totally or partially within the area of the proposed facility.

Source: SL 1977, ch 390, §9; SL 2006, ch 242, §4; SL 2008, ch 246, §2; SL 2019, ch 200, §5.