46-4-6. Time for construction and completion of dam.
Any person appropriating the waters of any dry-draw or watercourse within this state, within sixty days after the filing of the notice provided for in §§46-4-3 and 46-4-4, shall begin the construction of the dam mentioned in §46-4-1 for the storage or diversion of the waters, shall proceed diligently to complete the dam and shall divert the waters for beneficial use as rapidly as possible.
Source: SDC 1939, §61.0133; SL 1955, ch 430, §1; SL 1957, ch 490, §3; SL 1959, ch 451; SDC Supp 1960, §61.0138 (1); SL 1983, ch 318, §7.