A governmental entity may provide in a development impact fee ordinance the method for collection of development impact fees including, but not limited to:

(1) additions to the fee for reasonable interest and penalties for nonpayment or late payment;

(2) withholding of the certificate of occupancy, or building permit if no certificate of occupancy is required, until the development impact fee is paid;

(3) withholding of utility services until the development impact fee is paid; and

(4) imposing liens for failure to pay timely a development impact fee.

HISTORY: 1999 Act No. 118, Section 1.