Hearing on new schedule of rates; time for Commission action.

Checkout our iOS App for a better way to browser and research.

(A) Whenever there is filed with the commission by any telephone utility a schedule stating a new rate or rates which affect the telephone utility's general body of subscribers, the commission shall, after notice to the Office of Regulatory Staff and the public such as the commission may prescribe, hold a hearing concerning the lawfulness or reasonableness of the rate or rates; provided, however, that when the proposed rate or tariff is a proposal to institute or modify an offering or regulation that is not part of a general rate case and does not affect the telephone utility's general body of subscribers, the commission may approve such filing without a hearing. Whenever a new rate is requested which affects the telephone utility's general body of subscribers, the commission shall rule and issue its order approving or disapproving the changes in full or in part within six months of the time of filing.

(B) Should the Commission determine that it cannot, due to circumstances reasonably beyond its control, issue such order within the six-month period prescribed by this section, the Commission, may, by order, extend the six-month period for an additional five days. Any such order shall set forth such circumstances and make appropriate findings concerning the need for the extended period.

If the Commission rules and issues its order within the time aforesaid, and the utility shall appeal from the order, by filing with the Commission a petition for rehearing, the utility may put the rates requested in its schedule into effect under bond only during the appeal and until final disposition of the case. Such bond must be in a reasonable amount approved by the Commission, with sureties approved by the Commission, conditioned upon the refund, in a manner to be prescribed by order of the Commission, to the persons, corporations, or municipalities respectively entitled to the amount of the excess, if the rate or rates put into effect are finally determined to be excessive; or there may be substituted for the bond other arrangements satisfactory to the Commission for the protection of parties interested. During any period in which a utility shall charge increased rates under bond, it shall provide records or other evidence of payments made by its subscribers or patrons under the rate or rates which the utility has put into operation in excess of the rate or rates in effect immediately prior to the filing of the schedule.

All increases in rates put into effect under the provisions of this section which are not approved and for which a refund is required shall bear interest at a rate of twelve percent per annum. The interest shall commence on the date the disallowed increase is paid and continue until the date the refund is made.

In all cases in which a refund is due, the Commission shall order a total refund of the difference between the amount collected under bond and the amount finally approved.

(C) If the Commission fails to rule or issue its order within the time prescribed in subsection (A) or (B) of this section, the utility may put into effect the change in rates it requested in its schedule. The change is to be treated as an approval of the new rate schedule by the Commission.

(D) After the date the schedule, which affects the telephone utility's general body of subscribers, is filed with the Commission, no further rate change request which affects the telephone utility's general body of subscribers may be filed until twelve months have elapsed from the date of the filing of the schedule; provided, however, this section shall not apply to a request for rate reduction.

(E) The commission's determination of a fair rate of return must be documented fully in its findings of fact and based exclusively on reliable, probative, and substantial evidence on the whole record.

HISTORY: 1962 Code Section 58-404; 1952 Code Section 58-404; 1950 (46) 2466; 1983 Act No. 138 Section 3, eff June 15, 1983; 1989 Act No. 184, Section 3, eff June 8, 1989; 2006 Act No. 318, Section 45, eff May 24, 2006.