The denial of a project development application, application, or combined application under this article shall not preclude the utility from filing a new or amended project development application, application, or combined application at any time. A utility may proceed to construct a plant even if assurance of prudency or cost recovery under this article is not sought or is denied, and the failure to seek or obtain such an assurance may not be used as evidence or precedent in any future proceeding.
HISTORY: 2007 Act No. 16, Section 2, eff upon approval (became law without the Governor's signature on May 3, 2007).