(A) The provisions of this section apply to the collocation of small wireless facilities on an authority pole in the ROW by a wireless provider.
(B) A person owning, managing, or controlling authority poles in the ROW may not enter into an exclusive arrangement with any person for the right to attach to such poles. A person who purchases or otherwise acquires an authority pole is subject to the requirements of this section.
(C) Subject to an authority's ability to deny a permit application as set forth in this article, an authority shall allow the collocation of small wireless facilities on authority poles on nondiscriminatory terms and conditions in compliance with this article.
(D) The rates to collocate on authority poles must be nondiscriminatory regardless of the services provided by the collocating wireless provider and must be as set forth in Section 58-11-850.
(E)(1) The rates, fees, terms, and conditions for make-ready work to collocate on an authority pole must be nondiscriminatory, competitively neutral, commercially reasonable, and in compliance with this article.
(2)(a) The authority shall provide a good faith estimate for any make-ready work necessary to enable the pole to support the requested collocation by a wireless provider, including pole replacement if necessary, within sixty days after receipt of a complete application. Alternatively, the authority may require the wireless provider to perform the make-ready work and notify the wireless provider of such within the sixty-day period. If the wireless provider or its contractor performs the make-ready work, the wireless provider shall indemnify the authority for any negligence by the wireless provider or its contractor in the performance of such make-ready work and the work shall otherwise comply with applicable law.
(b) Make-ready work performed by or on behalf of an authority, including any pole replacement, must be completed within sixty days of written acceptance of the good faith estimate by the applicant. An authority may require replacement of the authority pole only if it demonstrates that the collocation would make the authority pole structurally unsound.
(3) The person owning, managing, or controlling the authority pole must not require more make-ready work than required to meet applicable codes or industry standards. Fees assessed by or on behalf of an authority for make-ready work, including any pole replacement, must not:
(a) include costs related to preexisting or prior damage or noncompliance;
(b) exceed either actual costs or the amount charged to other communications service providers for similar work on similar types of authority poles; or
(c) include any revenue or contingency-based consultant's fees or expenses of any kind.
(4) A wireless provider collocating on an authority pole pursuant to this article is responsible for reimbursing third parties for their actual and reasonable costs of any make-ready work reasonably required by the third party to accommodate the collocation. If the authority includes such costs of a third party in the good faith estimate provided pursuant to item (2), payment of that estimate to the authority constitutes reimbursement of the third party by the wireless provider. Otherwise, the third party may bill the wireless provider for such reimbursement within six months of the completion of the third party's make-ready work.
HISTORY: 2020 Act No. 179 (H.4262), Section 1, eff September 29, 2020.