A certificate of exploration issued by the department is required for exploration activities in an affected area of two acres or less and involving the development of open pits, trenches, open cuts, or tunneling. A certificate of exploration is not required for exploration activity on an area already covered by an operating permit or for (1) drilling core holes, (2) drilling bore holes, or (3) conducting geophysical and geochemical sampling and analysis.

An explorer engaging in exploration regulated pursuant to this section shall make a written application to the department for a certificate of exploration. The application must be on a form furnished by the department and must state fully the information requested. The applicant may be required to furnish other information as may be necessary to the department in order to enforce this chapter adequately. If the explorer does not receive notification of denial of the certificate of exploration within fifteen calendar days of the tendering of the application, the application is approved. If the certificate of exploration is denied, the department shall state the reasons, and the explorer must be given an additional thirty calendar days to either appeal the decision as set forth in Section 48-20-190 or modify its application for reconsideration by the department.

The application must be accompanied by a reclamation plan on forms furnished by the department. The department shall approve reclamation plans in accordance with Section 48-20-90.

Public notice and public hearing requirements of this chapter do not apply to an application for a certificate of exploration or the processing or granting of the certificate. The department shall treat the application for a certificate of exploration and the certificate, if any, and any material submitted with the application, as confidential trade secrets and proprietary business information of the applicant. The application and the certificate, if any, and any material submitted with the application is exempt from disclosure under the Freedom of Information Act and is not part of the public record.

Upon approval of an application for a certificate of exploration, the department shall require a performance bond or other security in an amount, and pursuant to requirements, set forth in Section 48-20-110.

An explorer engaging in exploration involving an affected area greater than two acres is required to obtain an operating permit in accordance with the procedures set forth in Sections 48-20-60 and 48-20-70.

HISTORY: 1990 Act No. 454, Section 2.