Right of entry for inspection; issuance of stop work order and notification of chapter requirements in event of noncompliance.

Checkout our iOS App for a better way to browser and research.

(A) The implementing agency shall have the right of entry for the purpose of determining if a land disturbing activity is being conducted without an approved stormwater management and sediment control plan, conducting inspections and taking enforcement actions.

(B) Upon inspection, if the implementing agency determines that a land disturbing activity is taking place without an approved stormwater management and sediment control plan, the implementing agency shall post a stop work order at the site of the land disturbing activity and shall notify the person responsible for the land disturbing activity of the requirements to submit a stormwater management and sediment control plan to the implementing agency and receive approval prior to resuming the land disturbing activity and the requirement to correct all violations.

HISTORY: 1991 Act No. 51, Section 2.


Download our app to see the most-to-date content.