Time for filing responses; inspection of defect and access to make repairs; time for reaching settlement.

Checkout our iOS App for a better way to browser and research.

(A) The contractor, subcontractor, supplier, or design professional has sixty days from service of the initial notice of claim to inspect, offer to remedy, offer to settle with the claimant, or deny, in whole or in part, the claim regarding the defects. Within sixty days from the service of the initial notice of claim, the contractor, subcontractor, supplier, or design professional shall serve written notice on the claimant of the contractor's, supplier's, or design professional's election pursuant to this section. The claimant shall allow inspection of the construction defect at an agreeable time, during normal business hours, to any party, if requested pursuant to this section. The claimant shall give the contractor, subcontractor, supplier, or design professional reasonable access to the property for inspection and if repairs have been agreed to by the parties, reasonable access to effect repairs. Failure to respond within sixty days is considered a denial of the claim.

(B) The claimant shall serve a response to the contractor's, subcontractor's, supplier's, or design professional's offer within ten days of receipt of the offer.

(C) If the parties cannot agree to settle the dispute pursuant to this article within ninety days after service of the initial notice of claim on the contractor, subcontractor, supplier, or design professional, the claim is considered denied and the claimant may proceed with a civil action or other remedy provided by contract or by law.

(D) An offer of settlement, repair, or remedy pursuant to this section is not admissible as evidence in any proceeding.

HISTORY: 2006 Act No. 371, Section 1.