If, after making a summary investigation, the division becomes satisfied that sufficient grounds exist to warrant a formal hearing being ordered as to the matters so investigated, it shall furnish to the public utility interested, a statement notifying the public utility of the matters under investigation. Ten (10) days after the notice has been given, the division may proceed to set a time and place for a hearing and investigation.
History of Section.
P.L. 1912, ch. 795, § 27; G.L. 1923, ch. 253, § 27; G.L. 1938, ch. 122, § 24; G.L. 1956, § 39-4-14.