(a) The facility is located on an existing irrigation diversion facility or structure constructed by persons.
(b) The operation of the facility would not require any water in addition to water appropriated for irrigation purposes.
(c) Operation of the facility would be limited to the period of time during which water is diverted for irrigation purposes and the diversion would not be extended for the purpose of hydroelectric power generation.
(2) Subsection (1) of this section shall not apply to the construction and maintenance of or the issuance of a permit for a hydroelectric facility or structure for which the hearing record is closed on or before the July 12, 1985, whether or not the record is later reopened by or at the direction of the Water Resources Commission for any reason.
(3) As used in this section, "Upper Deschutes River" means that portion of the mainstem Deschutes River between the North Canal Dam at approximately river mile 165 and the head waters of the Deschutes River. [1985 c.560 §3]
Note: 543.175 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 543 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.