Cancellation of permit for failure of proof of completion of appropriation; issuance of limited certificate; contest of issuance of certificate; exception for municipalities.

Checkout our iOS App for a better way to browser and research.


(2) The department may determine the extent to which an appropriation has been perfected under any permit at the time of submission of final proof provided for in ORS 537.250, and shall limit the certificate provided for in that section to a description of such appropriation as has been actually perfected to the extent that the water applied for has been actually applied to the beneficial use contemplated in the permit.

(3) Any person owning an application, permit or water right certificate subsequent in priority may jointly or severally contest before the department the issuance of the water right certificate at any time before it has issued, and after the time has expired for the completion of the appropriation under the permit, or within three months after issuance of the certificate. The contest shall be brought upon application made, and hearing shall be had in the same manner and after notice as provided in ORS 537.420 for proceedings for cancellation of permits. The department, in a final order, may cancel the permit or determine the extent to which the appropriation claimed thereunder has been perfected, and issue a water right certificate accordingly, or if a certificate has been issued, in the case of a contest within three months after its issuance, the department may cancel the water right certificate, or affirm its issuance, and if the water right certificate in such case is canceled, the permit upon which it is based shall also be canceled.

(4) A municipality may partially perfect not less than 25 percent of the water authorized by its permit without loss of priority or cancellation of the municipality’s permit under this section. If a municipality defers perfection of its water right under this section, the department shall issue a certificate under ORS 537.250 only for the amount perfected. Upon perfection of the deferred amount, the municipality shall request a water right certificate for the remaining portion of the water applied for in the original permit application. As used in this section, "municipality" includes a city, a port formed under ORS 777.005 to 777.725 and 777.915 to 777.953, a domestic water supply district formed under ORS chapter 264 or a water authority formed under ORS chapter 450. [Amended by 1983 c.740 §211; 1985 c.673 §38; 1989 c.707 §2; 1991 c.249 §43; 1993 c.577 §35; 1995 c.416 §37]


Download our app to see the most-to-date content.