Notice of violation; correction; when use prohibited; appeal.

Checkout our iOS App for a better way to browser and research.


(2) If no immediate hazard to health and safety is evident, the notice shall state that correction of the defective condition is required within 30 days of the date of the inspection. If the correction is not completed within the 30-day period, the owner or user of the boiler or pressure vessel may apply to the chief boiler inspector for extension of the time for making the correction. If the chief boiler inspector determines that corrective action was commenced within the time period specified in the notice, an extension may be granted for such time as is required to complete corrective action.

(3) If an immediate hazard to health and safety is evident, the notice shall prohibit further use of the boiler or pressure vessel. The inspector immediately shall report that action to the chief boiler inspector.

(4) If any person is aggrieved by a determination made upon inspection under this section, the person first shall appeal that determination to the chief boiler inspector and then to the Board of Boiler Rules. Subsequent appeal shall be as provided in ORS 183.480 to 183.540. [1983 c.676 §28]


Download our app to see the most-to-date content.