Inspections; testing; rules.

Checkout our iOS App for a better way to browser and research.


(2) Pressure piping that is nonboiler external piping, but that excludes potable water nonboiler external piping, shall be inspected on installation only and may not thereafter be considered as part of the boiler for the purposes of any subsequent inspections required by this section.

(3) If a hydrostatic test is necessary to determine the safety of a boiler or pressure vessel, the test shall be made by the owner or user of the boiler or pressure vessel and witnessed by a deputy or special inspector.

(4) All boilers and pressure vessels to be installed in this state shall be inspected during construction:

(a) By an inspector authorized to inspect boilers in this state or authorized under ORS 455.715 to 455.740 to perform inspections of boilers and pressure vessels identified by rule as provided in ORS 480.525 (5); or

(b) If constructed outside of the state, by an inspector holding a certificate of competency issued by a state that has a standard of examination substantially equal to that of this state. [1961 c.485 §17; 1969 c.582 §10; 1973 c.830 §3a; 1983 c.676 §11; 1991 c.518 §9; 2007 c.487 §6; 2009 c.696 §14]


Download our app to see the most-to-date content.