PCB facility permit fee.

Checkout our iOS App for a better way to browser and research.


(a) Secure performance of permit requirements;

(b) Close the facility;

(c) Provide for any monitoring or security of the facility after closure; and

(d) Provide for any remedial action by the state necessary after closure to protect the public health and safety and the environment.

(2) The amount so paid shall be held in a separate account and when the amount paid in by the permittee together with the earnings thereon equals the amount of the financial assurance required under ORS 466.320, the permittee shall be allowed to withdraw the financial assurance.

(3) If the facility is closed before the fees reach an amount equal to the financial assurance, appropriate adjustment shall be made and the reduced portion of the financial assurance may be withdrawn. [1985 c.670 §32; 1987 c.284 §4; 1987 c.540 §51]