Ineligibility for public works contracts for failure to pay or post notice of prevailing rates of wage; certified payroll reports to commissioner.

Checkout our iOS App for a better way to browser and research.


(a) The contractor or subcontractor intentionally failed or refused to pay the prevailing rate of wage to workers employed upon public works;

(b) The contractor failed to pay to the contractor’s employees amounts required under ORS 279C.840 and a surety or another person paid the amounts on the contractor’s behalf;

(c) The subcontractor failed to pay to the subcontractor’s employees amounts required under ORS 279C.840 and the contractor, a surety or another person paid the amounts on the subcontractor’s behalf;

(d) The contractor or subcontractor intentionally failed or refused to post the prevailing rates of wage as required under ORS 279C.840 (4); or

(e) The contractor or subcontractor intentionally falsified information in the certified statements the contractor or subcontractor submitted under ORS 279C.845.

(2) The commissioner shall maintain a written list of the names of contractors and subcontractors the commissioner determines are ineligible under this section and the period of time for which the contractors and subcontractors are ineligible. The commissioner shall publish the list, furnish a copy of the list upon request and make the list available to contracting agencies.

(3) If a contractor or subcontractor is a corporation or a limited liability company, the provisions of this section apply to any corporate officer or agent of the corporation or any member or manager of the limited liability company who is responsible for failing or refusing to pay or post the prevailing rate of wage, failing to pay to the contractor’s employees amounts required under ORS 279C.840 that a surety or other person pays on the contractor’s behalf, failing to pay to a subcontractor’s employees amounts required under ORS 279C.840 that the contractor, a surety or another person pays on the subcontractor’s behalf or intentionally falsifying information in the certified statements the contractor or subcontractor submits under ORS 279C.845.

(4) For good cause shown, the commissioner may remove the name of a contractor or subcontractor from the ineligible list.

(5) If a prevailing rate of wage claim is filed or the commissioner receives evidence indicating that a violation has occurred, a contractor or subcontractor required to pay the prevailing rate of wage to workers employed upon public works under ORS 279C.800 to 279C.870 shall send a certified copy of the payroll for workers employed upon public works when the commissioner requests the certified copy. [2003 c.794 §174; 2009 c.107 §1; 2013 c.239 §1; 2017 c.334 §5]