Action on contractor’s public works bond or payment bond; time limitation.

Checkout our iOS App for a better way to browser and research.


(2) The action shall be on the relation of the commissioner, the claimant, or that person’s assignee, as the case may be, and shall be in the name of the contracting agency that let the contract or, when applicable, the public agency or agencies for whose benefit the contract was let. It may be prosecuted to final judgment and execution for the use and benefit of the commissioner or the claimant, or that person’s assignee, as the fact may appear.

(3) The action shall be instituted no later than two years after the person last provided labor or materials or two years after the worker listed in the commissioner’s notice of claim last provided labor. [2003 c.794 §156; 2005 c.360 §5]