Right of action on payment bond or public works bond of contractor or subcontractor; notice of claim.

Checkout our iOS App for a better way to browser and research.


(a) The person or the assignee of the person has not been paid in full; and

(b) The person gives written notice of claim, as prescribed in ORS 279C.605, to the contractor and the contracting agency.

(2) When, upon investigation, the Commissioner of the Bureau of Labor and Industries has received information indicating that one or more workers providing labor on a public works have not been paid in full at the prevailing rate of wage or overtime wages, the commissioner has a right of action first on the contractor’s public works bond required under ORS 279C.836 and then, for any amount of a claim not satisfied by the public works bond, on the contractor’s payment bond, as provided in ORS 279C.380 and 279C.400. When an investigation indicates that a subcontractor’s workers have not been paid in full at the prevailing rate of wage or overtime wages, the commissioner has a right of action first on the subcontractor’s public works bond and then, for any amount of a claim not satisfied by the subcontractor’s public works bond, on the contractor’s payment bond. The commissioner’s right of action exists without necessity of an assignment and extends to workers on the project who are not identified when the written notice of claim is given, but for whom the commissioner has received information indicating that the workers have provided labor on the public works and have not been paid in full. The commissioner shall give written notice of the claim, as prescribed in ORS 279C.605, to the contracting agency, the Construction Contractors Board, the contractor and, if applicable, the subcontractor. The commissioner may not make a claim for the same unpaid wages against more than one bond under this section. [2003 c.794 §154; 2005 c.360 §3]


Download our app to see the most-to-date content.