Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints.

Checkout our iOS App for a better way to browser and research.


(2) Every public improvement contract must contain a clause or condition that, if the contractor or a first-tier subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract within 30 days after receiving payment from the contracting agency or a contractor, the contractor or first-tier subcontractor owes the person the amount due plus interest charges that begin at the end of the 10-day period within which payment is due under ORS 279C.580 (4) and that end upon final payment, unless payment is subject to a good faith dispute as defined in ORS 279C.580. The rate of interest on the amount due is nine percent per annum. The amount of interest may not be waived.

(3) Every public improvement contract and every contract related to the public improvement contract must contain a clause or condition that, if the contractor or a subcontractor fails, neglects or refuses to pay a person that provides labor or materials in connection with the public improvement contract, the person may file a complaint with the Construction Contractors Board, unless payment is subject to a good faith dispute as defined in ORS 279C.580.

(4) Paying a claim in the manner authorized in this section does not relieve the contractor or the contractor’s surety from obligation with respect to an unpaid claim. [2003 c.794 §140; 2005 c.103 §28; 2012 c.4 §1]


Download our app to see the most-to-date content.