Action against successful bidder; amount of damages; when action to be commenced; defenses.

Checkout our iOS App for a better way to browser and research.


(2) A person bringing an action under this section must establish a violation of ORS 279C.840, 316.167, 656.017, 657.505, 701.021 or 701.026 by a preponderance of the evidence.

(3) Upon establishing that the violation occurred, the person shall recover, as liquidated damages, 10 percent of the total amount of the contract or $5,000, whichever is greater.

(4) In any action under this section, the prevailing party is entitled to an award of reasonable attorney fees.

(5) An action under this section must be commenced within two years of the substantial completion of the construction, repair, remodeling, alteration, conversion, modernization, improvement, rehabilitation, replacement or renovation. For the purposes of this subsection, "substantial completion" has the meaning given that term in ORS 12.135.

(6) A person may not recover any amounts under this section if the defendant in the action establishes by a preponderance of the evidence that the plaintiff:

(a) Was in violation of ORS 701.021 or 701.026 at the time of making the bid or proposal on the contract;

(b) Was in violation of ORS 316.167, 656.017 or 657.505 with respect to any employees of the plaintiff as of the time of making the bid or proposal on the contract; or

(c) Was in violation of ORS 279C.840 with respect to any contract performed by the plaintiff within one year before making the bid or proposal on the contract at issue in the action. [2003 c.794 §135; 2007 c.836 §44]