(2) The governing body of a city or its designee shall take final action on a supplemental application submitted under this section, including resolution of all appeals, within 240 days after the application is deemed complete. Except that 240 days shall substitute for 120 days, all other applicable provisions of ORS 227.178 shall apply to a supplemental application submitted under this section.
(3) A supplemental application submitted under this section shall include a request for any rezoning or zoning variance that may be required to issue a permit under the city’s comprehensive plan and land use regulations.
(4) The governing body of a city or its designee shall adopt specific findings describing the reasons for approving or denying:
(a) A use for which approval is sought under this section; and
(b) A rezoning or variance requested in the application. [1999 c.648 §4]