Effective: May 17, 2021
Latest Legislation: House Bill 2 - 134th General Assembly
Unless a modification by an electric cooperative is necessary for an electric service that uses smart grid or other technology, a party with a preexisting attachment to a pole is not required to bear any of the costs of rearranging or replacing its attachment if the rearrangement or replacement is necessary because of another party's request for an additional attachment or a modification of an existing attachment.
Last updated June 9, 2021 at 2:09 PM