Revocation or suspension of permits; orders to cease and desist; injunction.

Checkout our iOS App for a better way to browser and research.

A. The state engineer may periodically review a project to determine if the permittee is complying with the terms and conditions of the permit. The state engineer may permanently revoke or temporarily suspend a permit for good cause after an investigation and a hearing before the state engineer or a hearing officer appointed by him. Notice shall be sent, by certified mail, to the permittee at least thirty days before any hearing on a revocation or suspension disclosing the permittee's alleged failure to comply with the permit's terms and conditions.

B. Except as otherwise provided in this section, if the state engineer has reason to believe that a person or governmental entity has violated a provision of the Ground Water Storage and Recovery Act or a permit issued or regulation adopted pursuant to that act, the state engineer may issue a written notice that the person or governmental entity appear and show cause, at a hearing before the state engineer not less than fifteen days after the receipt of the notice, why the person or governmental entity should not be ordered to cease and desist from the violation. The notice shall inform the person or governmental entity of the date, time and place of the hearing and the consequences of the person's or governmental entity's failure to appear.

C. If the state engineer finds that a person or governmental entity is constructing or operating a project in violation of the Ground Water Storage and Recovery Act, the state engineer may issue a temporary order for the person or governmental entity to cease and desist the construction or operation pending final action by the state engineer pursuant to this section. The order shall include written notice to the person or governmental entity of the date, time and place where the person or governmental entity shall appear at a hearing before the state engineer to show cause why the temporary order should be vacated. The hearing shall be held not less than fifteen days after the date of the order.

D. After a hearing pursuant to this section, or after the expiration of the time to appear, the state engineer shall issue a decision and order. The decision and order shall be in a form as the state engineer determines to be reasonable and appropriate and may include a determination of violation, an order to cease and desist, the recommendation of a civil penalty and an order directing that positive steps be taken to abate or ameliorate any harm or damage arising from the violation. Any person or governmental entity affected may appeal the decision to the district court pursuant to Section 72-7-1 NMSA 1978.

E. If a person or governmental entity continues a violation after the state engineer has issued a decision and order pursuant to this section or a temporary order pursuant to this section, the state engineer may apply for a temporary restraining order or a preliminary or permanent injunction from the district court. A decision to seek injunctive relief does not preclude other forms of relief or enforcement against a violator.

History: Laws 1999, ch. 285, § 11.

ANNOTATIONS