Establishment of mandatory remediation timeframes.

Checkout our iOS App for a better way to browser and research.

58:10C-28 Establishment of mandatory remediation timeframes.

28. a. The department shall establish mandatory remediation timeframes, and expedited site specific timeframes when necessary, to protect the public health and safety and the environment, for each of the following:

(1) a receptor evaluation;

(2) control of ongoing sources of contamination;

(3) establishment of interim remedial measures;

(4) addressing immediate environmental concern conditions;

(5) the performance of each phase of the remediation including preliminary assessment, site investigation, remedial investigation and remedial action;

(6) completion of remediation; and

(7) any other activities deemed necessary by the department to effectuate timely remediation.

b. In establishing remediation timeframes pursuant to subsection a. of this section, the department shall take the following into account:

(1) the potential risk to the public health, safety, and the environment;

(2) the results of the receptor evaluation;

(3) the ongoing industrial or commercial operations at the site;

(4) whether, for operating industrial or commercial facilities, there are no releases of contamination to the groundwater or surface water from the site; and

(5) the complexity of the contaminated site.

c. The department shall grant an extension to a mandatory remediation timeframe as a result of:

(1) a delay by the department in reviewing or granting a permit, provided that there was a timely filing of a technically and administratively complete permit application;

(2) a delay in the provision of State funding for remediation, provided that there was a timely filing of a technically and administratively complete application for funding; or

(3) a delay by the department for an approval or permit required for long-term operation, maintenance and monitoring of an engineering control at the site provided the request for approval or permit application is technically and administratively complete.

d. The department may grant an extension to a mandatory remediation timeframe on a case-by case basis as a result of:

(1) a delay in obtaining access to property, provided the person responsible for conducting the remediation demonstrates that good faith efforts have been undertaken to gain access, access has not been granted by the property owner, and, after good faith efforts have been exhausted, a complaint was filed with the Superior Court to gain access, in accordance with applicable rules and regulations;

(2) other circumstances beyond the control of the person responsible for conducting the remediation, such as fire, flood, riot, or strike; or

(3) other site-specific circumstances that may warrant an extension as determined by the department.

L.2009, c.60, s.28.


Download our app to see the most-to-date content.