Requirements for permit applicants.

Checkout our iOS App for a better way to browser and research.

13:1D-160 Requirements for permit applicants.

4. a. Beginning immediately upon the adoption of the rules and regulations required pursuant to section 5 of this act, the department shall not consider complete for review any application for a permit for a new facility or for the expansion of an existing facility, or any application for the renewal of an existing facility's major source permit, if the facility is located, or proposed to be located, in whole or in part, in an overburdened community, unless the permit applicant first:

(1) Prepares an environmental justice impact statement that assesses the potential environmental and public health stressors associated with the proposed new or expanded facility, or with the existing major source, as applicable, including any adverse environmental or public health stressors that cannot be avoided if the permit is granted, and the environmental or public health stressors already borne by the overburdened community as a result of existing conditions located in or affecting the overburdened community;

(2) Transmits the environmental justice impact statement required to be prepared pursuant to paragraph (1) of this subsection, at least 60 days in advance of the public hearing required pursuant to paragraph (3) of this subsection, to the department and to the governing body and the clerk of the municipality in which the overburdened community is located. Upon receipt, the department shall publish the environmental justice impact statement on its Internet website; and

(3) Organizes and conducts a public hearing in the overburdened community. The permit applicant shall publish a notice of the public hearing in at least two newspapers circulating within the overburdened community, including one local non-English language newspaper, if applicable, not less than 60 days prior to the public hearing. The permit applicant shall provide a copy of the notice to the department, and the department shall publish the notice on its Internet website and in the monthly bulletin published pursuant to section 6 of P.L.1975, c.232 (C.13:1D-34). The notice of the public hearing shall provide the date, time, and location of the public hearing, a description of the proposed new or expanded facility or existing major source, as applicable, a map indicating the location of the facility, a brief summary of the environmental justice impact statement, information on how an interested person may review a copy of the complete environmental justice impact statement, an address for the submittal of written comments to the permit applicant, and any other information deemed appropriate by the department. At least 60 days prior to the public hearing, the permit applicant shall send a copy of the notice to the department and to the governing body and the clerk of the municipality in which the overburdened community is located. The applicant shall invite the municipality to participate in the public hearing. At the public hearing, the permit applicant shall provide clear, accurate, and complete information about the proposed new or expanded facility, or existing major source, as applicable, and the potential environmental and public health stressors associated with the facility. The permit applicant shall accept written and oral comments from any interested party, and provided an opportunity for meaningful public participation at the public hearing. The permit applicant shall transcribe the public hearing and, no later than 10 days after the public hearing, submit the transcript along with any written comments received, to the department. Following the public hearing, the department shall consider the testimony presented and any written comments received, and evaluate the issuance of, or conditions to, the permit, as necessary in order to avoid or reduce the adverse environmental or public health stressors affecting the overburdened community.

The department may require the applicant to consolidate the public hearing held pursuant to this paragraph with any other public hearing held or required by the department regarding the permit application, provided the public hearing meets the other requirements of this paragraph. The department shall consider a request by a permit applicant to consolidate required public hearings and, if the request is granted by the department, the consolidation shall not preclude an application from being deemed complete for review pursuant to subsection a. of this section.

b. Notwithstanding the provisions of P.L.1975, c.232 (C.13:1D-29 et seq.) or any other law, or rule or regulation adopted pursuant thereto, to the contrary, the department shall not issue a decision on an application for a permit for a new facility or for the expansion of an existing facility, or on an application for the renewal of an existing facility's major source permit, if such facility is located, or proposed to be located, in whole or in part in an overburdened community until at least 45 days after the public hearing held pursuant to paragraph (3) of subsection a. of this subsection.

c. Notwithstanding the provisions of any other law, or rule or regulation adopted pursuant thereto, to the contrary, the department shall, after review of the environmental justice impact statement prepared pursuant to paragraph (1) of subsection a. of this section and any other relevant information, including testimony and written comments received at the public hearing, deny a permit for a new facility upon a finding that approval of the permit, as proposed, would, together with other environmental or public health stressors affecting the overburdened community, cause or contribute to adverse cumulative environmental or public health stressors in the overburdened community that are higher than those borne by other communities within the State, county, or other geographic unit of analysis as determined by the department pursuant to rule, regulation, or guidance adopted or issued pursuant to section 5 of this act, except that where the department determines that a new facility will serve a compelling public interest in the community where it is to be located, the department may grant a permit that imposes conditions on the construction and operation of the facility to protect public health.

d. Notwithstanding the provisions of any other law, or rule or regulation adopted pursuant thereto, to the contrary, the department may, after review of the environmental justice impact statement prepared pursuant to paragraph (1) of subsection a. of this section and any other relevant information, including testimony and written comments received at the public hearing, apply conditions to a permit for the expansion of an existing facility, or the renewal of an existing facility's major source permit, concerning the construction and operation of the facility to protect public health, upon a finding that approval of a permit or permit renewal, as proposed, would, together with other environmental or public health stressors affecting the overburdened community, cause or contribute to adverse cumulative environmental or public health stressors in the overburdened community that are higher than those borne by other communities within the State, county, or other geographic unit of analysis as determined by the department pursuant to rule, regulation, or guidance adopted or issued pursuant to section 5 of this act.

e. If a permit applicant is applying for more than one permit for a proposed new or expanded facility, the permit applicant shall only be required to comply with the provisions of this section once, unless the department, in its discretion, determines that more than one public hearing is necessary due to the complexity of the permit applications necessary for the proposed new or expanded facility. Nothing in this section shall be construed to limit the authority of the department to hold or require additional public hearings, as may be required by any other law, rule, or regulation.

f. Nothing in this section shall be construed to limit the right of an applicant to continue facility operations during the process of permit renewal to the extent such right is conveyed by applicable law, rule, or regulation, including the application shield provisions of the rules and regulations adopted pursuant to the "Air Pollution Control Act (1954)," P.L.1954, c.212 (C.26:2C-1 et seq.).

g. In addition to any other fee authorized by law, rule, or regulation, the department shall assess each permit applicant a reasonable fee in order to cover the department's costs associated with the implementation of this act, including costs to provide technical assistance to permit applicants and overburdened communities as needed to comply with this act.

L.2020, c.92, s.4.


Download our app to see the most-to-date content.