Facility for treatment of water acquired and constructed by county: Operation and maintenance of facility by public utility authorized; Commission’s approval of agreement for operation and maintenance required.

Checkout our iOS App for a better way to browser and research.

1. A public utility may enter into an agreement with a county to operate and maintain a facility acquired and constructed or to be acquired and constructed by a county pursuant to NRS 244.3661. The term of the agreement may be for more than 1 fiscal year. Any such agreement must be approved by the Commission before it becomes effective.

2. The Commission shall not approve an agreement executed pursuant to this section unless it determines that:

(a) The payments to be made under the agreement to the utility for operation and maintenance of the facility are reasonable and just; and

(b) The agreement is in the public interest.

(Added to NRS by 1991, 1942)


Download our app to see the most-to-date content.