Duty of utility to administer Program according to annual plan; recovery of costs by utility. [Effective through December 31, 2025.]

Checkout our iOS App for a better way to browser and research.

1. Each utility shall carry out and administer the Wind Demonstration Program within its service area in accordance with its annual plan as approved by the Commission pursuant to NRS 701B.610.

2. A utility may recover its reasonable and prudent costs, including, without limitation, customer incentives, that are associated with carrying out and administering the Program within its service area by seeking recovery of those costs in an appropriate proceeding before the Commission pursuant to NRS 704.110.

(Added to NRS by 2007, 2994; A 2011, 2562; 2013, 3346)


Download our app to see the most-to-date content.