46-1642. Livestock waste control facility; approvals required.

An applicant for a permit for a livestock waste control facility which includes a dam, holding pond, or lagoon for which approval by the Department of Natural Resources is not otherwise required but for which approval by the Department of Environment and Energy under section 54-2429 is required shall submit an application for approval along with plans, drawings, and specifications to the Department of Natural Resources and obtain approval from the Department of Natural Resources before beginning construction. The Department of Natural Resources shall approve or deny the dam, holding pond, or lagoon pursuant to this section within sixty days after such application is submitted.