69-4-402. Petition for relocation of overhead line. An owner of agricultural land across which an overhead utility line has been constructed may petition the district court for an order for relocation of the line for the purpose of installing an agricultural improvement. The petition shall set forth the nature of the proposed agricultural improvement, the increase in productivity of the land anticipated to result from the improvement, and a feasible alternative route, across other land to be provided by the petitioner at no cost to the owner of the overhead utility line.

History: En. 24-202 by Sec. 2, Ch. 123, L. 1975; R.C.M. 1947, 24-202.