Construction manager at risk method of project delivery; qualifications-based selection procedure for procuring architectural, engineering and land surveying services

Checkout our iOS App for a better way to browser and research.

  1. When used in this section, "construction manager at risk" means a method of project delivery in which a construction manager guarantees a maximum price for the construction of a project and in which the governing authority or board, before using this method of project delivery, shall include a detailed explanation of why using the construction manager at risk method of project delivery for a particular project satisfies the public need better than that traditional design-bid-build method based on the following criteria:
    1. The use of construction manager at risk for the project provides a savings in time or cost over traditional methods; and
    2. The size and type of the project is suitable for use of the construction management at risk method of project delivery.
  2. When the construction manager at risk method of project delivery is used:
    1. There may be a separate contract for design services and a separate contract for construction services;
    2. The contract for construction services may be entered into at the same time as a contract for the design services or later;
    3. Design and construction of the project may be in sequential or concurrent phases; and
    4. Finance, maintenance, operation, reconstruction or other related services may be included for a guaranteed maximum price.
  3. When procuring design professional services under a construction manager at risk project delivery method, the agency or governing authority shall procure the services of a design professional pursuant to qualifications-based selection procedures.
  4. Before the substantial completion of the design documents, the agency or governing authority may elect to hire a construction manager.
  5. When procuring construction management services, the agency or governing authority shall follow the qualifications-based selection procedures as outlined in subsection (10) of this section or the competitive sealed proposal procedures as outlined in Section 31-7-13.
  6. The agency or governing authority may require the architect or engineer and the construction manager, by contract, to cooperate in the design, planning and scheduling, and construction process. The contract shall not make the primary designer or construction manager a subcontractor or joint venture partner to the other or limit the primary designer's or construction manager's independent obligations to the agency or governing authority.
  7. Notwithstanding anything to the contrary in this chapter:
    1. Each project for construction under a construction manager at risk contract shall be a specific, single project with a minimum construction cost of Twenty-Five Million Dollars ($25,000,000.00).
    2. Each project under a construction manager at risk contract shall be a specific, single project. For the purposes of this paragraph, "specific, single project" means a project that is constructed at a single location, at a common location or for a common purpose.
  8. Agencies shall retain an independent architectural or engineering firm to provide guidance and administration of the professional engineering or professional architecture aspects of the project throughout the development of the scope, design, and construction of the project.
  9. The state shall, on an annual basis, compile and make public all proceedings, records, contracts and other public records relating to procurement transactions authorized under this section.
  10. For purposes of this section, the "qualifications-based selection procedure" shall include:
    1. Publicly announcing all requirements for architectural, engineering, and land surveying services, to procure these services on the basis of demonstrated competence and qualifications, and to negotiate contracts at fair and reasonable prices after the most qualified firm has been selected.
    2. Agencies or governing authorities shall establish procedures to prequalify firms seeking to provide architectural, engineering, and land surveying services or may use prequalification lists from other state agencies or governing authorities to meet the requirements of this section.
    3. Whenever a project requiring architectural, engineering, or land surveying services is proposed for an agency or governing authority, the agency or governing authority shall provide advance notice published in a professional services bulletin or advertised within the official state newspaper setting forth the projects and services to be procured for not less than fourteen (14) days. The professional services bulletin shall be mailed to each firm that has requested the information or is prequalified under Section 31-7-13. The professional services bulletin shall include a description of each project and shall state the time and place for interested firms to submit a letter of interest and, if required by the public notice, a statement of qualifications.
    4. The agency or governing authority shall evaluate the firms submitting letters of interest and other prequalified firms, taking into account qualifications. The agency or governing authority may consider, but shall not be limited to, considering:
      1. Ability of professional personnel;
      2. Past record and experience;
      3. Performance data on file;
      4. Willingness to meet time requirements;
      5. Location;
      6. Workload of the firm; and
      7. Any other qualifications-based factors as the agency or governing authority may determine in writing are applicable.

      The agency or governing authority may conduct discussions with and require public presentations by firms deemed to be the most qualified regarding their qualifications, approach to the project and ability to furnish the required services.

    5. The agency or governing authority shall establish a committee to select firms to provide architectural, engineering, and land surveying services. A selection committee may include at least one (1) public member nominated by a statewide association of the profession affected. The public member may not be employed or associated with any firm holding a contract with the agency or governing authority nor may the public member's firm be considered for a contract with that agency or governing authority while serving as a public member of the committee. In no case shall the agency or governing authority, before selecting a firm for negotiation under paragraph (f) of this section, seek formal or informal submission of verbal or written estimates of costs or proposals in terms of dollars, hours required, percentage of construction cost, or any other measure of compensation.
    6. On the basis of evaluations, discussions, and any presentations, the agency or governing authority shall select no less than three (3) firms that it determines to be qualified to provide services for the project and rank them in order of qualifications to provide services regarding the specific project. The agency or governing authority shall then contact the firm ranked most preferred to negotiate a contract at a fair and reasonable compensation. If fewer than three (3) firms submit letters of interest and the agency or governing authority determines that one (1) or both of those firms are so qualified, the agency or governing authority may proceed to negotiate a contract under paragraph (g) of this section.
    7. The agency or governing authority shall prepare a written description of the scope of the proposed services to be used as a basis for negotiations and shall negotiate a contract with the highest qualified firm at compensation that the agency or governing authority determines in writing to be fair and reasonable. In making this decision, the agency or governing authority shall take into account the estimated value, scope, complexity, and professional nature of the services to be rendered. In no case may the agency or governing authority establish a maximum overhead rate or other payment formula designed to eliminate firms from contention or restrict competition or negotiation of fees. If the agency or governing authority is unable to negotiate a satisfactory contract with the firm that is most preferred, negotiations with that firm shall be terminated. The agency or governing authority shall then begin negotiations with the firm that is next preferred. If the agency or governing authority is unable to negotiate a satisfactory contract with that firm, negotiations with that firm shall be terminated. The agency or governing authority shall then begin negotiations with the firm that is next preferred. If the agency or governing authority is unable to negotiate a satisfactory contract with any of the selected firms, the agency or governing authority shall reevaluate the architectural, engineering, or land surveying services requested, including the estimated value, scope, complexity, and fee requirements. The agency or governing authority shall then compile a second list of not less than three (3) qualified firms and proceed in accordance with the provisions of this section. A firm negotiating a contract with an agency or governing authority shall negotiate subcontracts for architectural, engineering, and land surveying services at compensation that the firm determines in writing to be fair and reasonable based upon a written description of the scope of the proposed services.
  11. The provisions of this section shall not affect any procurement by the Mississippi Transportation Commission.


Download our app to see the most-to-date content.