Sec. 71.

Not less than 10 days before taking reservations under a preliminary reservation agreement for a unit in a condominium project, recording a master deed for a project, or beginning construction of a project which is intended to be a condominium project at the time construction is begun, whichever is earliest, a written notice of the proposed action shall be provided to each of the following:

(a) The appropriate city, village, township, or county.

(b) The appropriate county road commission and county drain commissioner.

(c) The department of environmental quality.

(d) The state transportation department.

History: 1978, Act 59, Eff. July 1, 1978 ;-- Am. 1980, Act 513, Imd. Eff. Jan. 26, 1981 ;-- Am. 1982, Act 538, Imd. Eff. Jan. 17, 1983 ;-- Am. 2002, Act 283, Imd. Eff. May 9, 2002