Sec. 91.
(1) Except for section 89(5), sections 71 to 89 do not apply to a provider that each year pays not less than 2.0% of total utility sales revenues for the second year preceding, including electricity or natural gas commodity costs, to an independent energy waste reduction program administrator selected by the commission.
(2) An alternative compliance payment received from a provider by the energy waste reduction program administrator under subsection (1) shall be used to administer energy efficiency programs for the provider.
(3) The commission shall allow a provider to recover an alternative compliance payment under subsection (1). This cost shall be recovered from residential customers by volumetric charges, from all other metered customers by per-meter charges, and from unmetered customers by an appropriate charge. Fixed, per-meter charges under this subsection may vary by rate class. Charges under this subsection may be itemized on utility bills, but shall not be itemized on or after January 1, 2021.
(4) A provider's alternative compliance payment under subsection (1) shall only be used to fund energy waste reduction programs for that provider's customers. To the extent feasible, charges collected from a particular customer rate class and paid to the energy waste reduction program administrator under subsection (1) shall be devoted to energy waste reduction programs and services for that rate class.
(5) Money paid to the energy waste reduction program administrator under subsection (1) and not spent by the administrator that year shall remain available for expenditure the following year, subject to the requirements of subsection (4).
(6) The commission shall select a qualified nonprofit organization to serve as an energy waste reduction program administrator under this section, through a competitive bid process.
(7) The commission shall arrange for a biennial independent audit of the energy waste reduction program administrator.
History: 2008, Act 295, Imd. Eff. Oct. 6, 2008 ;-- Am. 2016, Act 342, Eff. Apr. 20, 2017