Bypassed Projects.

Checkout our iOS App for a better way to browser and research.

Sec. 5412.

(1) The department may bypass projects that fail to meet the schedule negotiated and agreed upon between the water supplier and the department, or that do not have approved project plans and specifications and an approvable application 90 days prior to the last day of the state fiscal year, whichever comes first.

(2) A water supplier may submit a written request to the department to extend a project schedule for not more than 60 days. The request shall provide the reason for the noncompliance with the schedule. A water supplier may file 1 additional 30-day extension request to its schedule.

(3) A project bypassed under this section shall not be considered for an order of approval until all other projects have either been funded or rejected. This section does not prohibit the inclusion of the project in the priority list of the next annual funding cycle or the resubmission of an application for assistance in the next annual funding cycle.

(4) The department shall provide affected water suppliers with a written notice of intent to bypass not less than 30 days before the bypass action.

(5) For projects bypassed under this section, the department shall transmit to the water supplier an official notice of bypass for the fundable project.

(6) A bypass action under this section does not modify any compliance dates established pursuant to a permit, order, or other document issued by the department or entered as part of an action brought by the state or a federal agency.

(7) After a project is bypassed, the department may award assistance to projects outside the fundable range. Assistance shall be made available to projects outside the fundable range in priority order contingent upon the supplier's satisfaction of all applicable requirements for assistance within the time period established by the department, but not to exceed 60 days from the date of notification. The department shall notify water suppliers with projects outside the fundable range of bypass action, of the amount of bypassed funds available for obligation, and of the deadline for submittal of a complete, approvable application.

History: Add. 1997, Act 26, Imd. Eff. June 17, 1997