Failure to commence construction or operation

Checkout our iOS App for a better way to browser and research.

    (a)    A certificate automatically shall be null and void if:

        (1)    Construction or other preparation of the site for its intended use of the facility for which the certificate was issued has not commenced within 2 years following issuance of the certificate; or

        (2)    The facility has not commenced operation within 4 years following issuance of the certificate.

    (b)    The Board may extend the time limits imposed under subsection (a) of this section if the certificate holder:

        (1)    Applies to the Board for an extension; and

        (2)    Shows good cause for allowing the extension.