Inspection and acceptance of work

Checkout our iOS App for a better way to browser and research.

RS 1596.12 - Inspection and acceptance of work

The governing authority shall provide for the final inspection of the work performed and the improvements made and, if the work is found to have been completed satisfactorily in accordance with the contract, as evidenced by a certificate of the project engineer, the governing authority shall by ordinance approve and accept the work and fulfill its obligations under the contract after compliance with laws relative to the completion of contracts involving public works by full payment therefor of any and all amounts and balances due the contractor, including all retained percentages of payments previously made thereon on engineer's estimates and which percentages were retained pending completion of the work.

Acts 1985, No. 979, §1.